The new machine at Strojírny Prostějov s.r.o. is now in operation. How did the preparation for the installation of the new horizontal boring mill WFT 13 R CNC from the Czech manufacturer Fermat unfold?
In this accelerated video sequence, you can see:
- The preparation of the foundations for the new machine… up to the current state, where the machine is already fully operational and production has reached a new level!
The standard delivery time for the machine, including the foundation, was 8 months, but it was reduced to 6 months, and the machine has been in operation since the beginning of December.